Nam Na Hydropower 2
Nam Na Hydropower Plant 2
Investor: Hung Hai Construction Co., Ltd
Capacity: 3x22MW
Contractor: LILAMA10 Joint Stock Company
Nam Na 2 hydropower project is located in Lai Chau province, started construction in May 2009 and is in the process of installing and finishing machines, with installed capacity Nlm=66MW.
The main parameters of the project:
- Installed capacity: Nlm=66 MW;
- Average annual electricity: E0=254.11 million KWh;
- Riverbed hydropower plant, 03 units, Kaplan turbine, vertical shaft;
- Structural weirs made of gravity concrete, dam crest elevation 264.5m, dam crest length 58m, maximum height 24.5m;
- Structural reinforced concrete spillway, non-vacuum Ofixerov type, overflow area 61m wide, maximum height 33.5m, has 4 overflow chambers, each cavity width 13m, radial gate opening and closing by hydraulic cylinder force;
- Design flood discharge volume Q0.5%=4.810 m3/s, test flood discharge Q0.1%= 6,120 m3/s;
- Maximum flow through the factory: Qmax= 444 m3/s;
- Commencement: May 2009
- Consultancy contents: Survey, technical design - preparation of total cost estimates, preparation of bidding documents for equipment, construction design and author supervision;