Tan Thang Cement Factory - Imprint of Lilama workers10
In just 17 months, from June 21, 2018 to November 17, 2019, Tan Thang Cement Factory (Quynh Luu, Nghe An), with a capacity of 5,000 tons of clinker/day, equivalent to 2 - 2, 5 million tons of cement/year has completed construction work. According to experts, this is a record construction progress in the history of Vietnam's cement industry with a total installation volume of 19,964 tons, a total processing volume of 15,266 tons.
1, Material crushing station: Lilama10 Joint Stock Company fabricated and installed
Item 311 – Quantitative grinding: All input materials after being imported into the warehouse (lime warehouse, clay warehouse, gypsum warehouse, ...) are transferred through conveyors to quantitative grinding. With the system of weighing bins and reversing conveyors, the right proportions will be distributed to transfer through the conveyor system 311.BC620 to the raw mill. The equipment is complicated, with many structures, but with the creative process, overcoming difficulties of LILAMA workers during the construction process, overcoming unfavorable conditions such as: construction in two consecutive rainy seasons; land clearance is difficult and slow compared to the committed schedule; There were big storms in the area causing heavy rain, forcing construction to stop. Especially, although the time when it is impossible to execute due to rain or storm is a force majeure event specified in the contract as 29 days, but with our experience, capacity and the unit has creative construction plans, shorten the progress, overcome the problems.
2, Material crusher: Lilama10 Joint Stock Company manufactures and installs
The raw mill system is rated as the most complex in the system of cement plants with many imported equipment such as crusher (89 tons), 3 grinding rollers (102 tons / 3 rollers), the whole system hydraulics, oil, pneumatics, etc.
As the backbone of the factory with the kiln and grinding system, it is very closely watched by foreign experts and investors. With creativity and experience through cement projects (But Son Cement - 2 lines, Xuan Thanh Cement with a capacity of 4.5 million tons/year, ...) so Lilama10 Joint Stock Company - Construction team Tan Thang Cement has completed the installation on schedule. The item is in the testing phase and is handed over to the investor.