Pha Lai II Thermal Power Plant

Project name: Pha Lai Thermal Power Plant 2

Investor: Electricity of Vietnam (EVN)

Main contractor: Hyundai Engineering & Construction Company (HDEC).

Location: Pha Lai Town, Hai Duong Province.

Time: 1999-2001

Describe:

This is the largest coal-fired power project in Vietnam invested by Vietnam Electricity. The 2x300MW power plant was built 65km northeast of Hanoi capital, with an investment value of about 540 million USD.

The new plant to replace the old one includes eight 220 ton/h coal-fired boilers and four 110MW turbines. The old factory built by the Soviet Union only operates at three-quarters of its capacity during the dry season.

Scope of work:

- Installation of technological equipment.

- Fabrication and installation of non-standard equipment and electrical system of boiler No. 2.