The Project Management Board of Power Project 2 (EVNPMB2) and Lilama 10 Joint Stock Company (LILAMA 10) have successfully installed the "heart of Unit 1" - the rotor of the generator for Unit 1 of the Ialy Hydropower Plant Expansion Project.
On July 26, 2024, the Project Management Board of Power Project 2 (EVNPMB2), in coordination with Lilama 10 Joint Stock Company (Lilama 10), successfully installed the rotor for Unit 1 at the Ialy Hydropower Plant Expansion Project.
According to the Site Commander of Lilama 10 Joint Stock Company, the rotor of Unit 1 has a total weight of over 400 tons and was installed into the stator using a 500-ton dual crane.
Before installing the rotor, Lilama 10 had completed the installation of the turbine, stator, and the powerhouse crane. The rotor and stator of the generator for Unit 1 underwent insulation and high-voltage testing in accordance with current standards.
The preparation and final inspection stages were carried out by Lilama 10's staff and workers with the utmost professionalism, care, and a strong sense of duty and responsibility.
The rotor was lifted and moved into its installation position
Chairman of the Board of Directors of Lilama 10, Mr. Dang Van Long (fourth from the left), inspected the installation process at the project site
The rotor was moved into the center of the stator for Unit 1
The rotor was successfully installed into the stator of Unit 1
Engineers, technicians, and workers of Lilama 10, with their expertise, skills, and professional demeanor, are currently aligning the final stages of the rotor installation into the stator
The leadership of EVNPMB2 presented flowers to the teams involved in the project after the successful installation of the rotor
With Lilama 10's successful installation of the rotor for Unit 1 of the Ialy Hydropower Plant Expansion Project, this marks a significant milestone in ensuring the schedule for the testing phase of Unit 1. This achievement supports the goal of having Unit 1 operational by November 2024.
Earlier, the Site Commander of Lilama 10 reported that the working wheel and stator of Unit 1 were successfully installed by Lilama 10's staff and workers at the project site on July 14, 2024, and July 20, 2024.
The working wheel for Unit 1 was positioned by Lilama 10 on July 14, 2024
In the early hours of July 20, 2024, Lilama 10 successfully installed the stator for Unit 1 into its position