LILAMA 10 Demonstrates Its Industrial Module Construction Capabilities at the TA’ZIZ Methanol Project in the UAE

03.11.2026

Building on its achievements in major green hydrogen projects in the United States and Saudi Arabia, LILAMA 10 Joint Stock Company continues to demonstrate its industrial module fabrication, construction and installation capabilities in the international market through its participation in the TA’ZIZ Methanol Project in Abu Dhabi, United Arab Emirates (UAE).

Artist’s Impression of the Project

The completion of more than 6,000 tonnes of structural steel, electrical systems and piping in Phase 1 by LILAMA 10 marks a significant milestone, demonstrating the Company’s capabilities in construction management, quality control and on-schedule delivery of large-scale industrial modules.

Modules fabricated and assembled by LILAMA 10 Joint Stock Company at Hyundai Eco Vina Co., Ltd., Quang Ngai Province, Viet Nam

A Large-Scale Chemical Project in the UAE

TA’ZIZ Methanol is the UAE’s first large-scale methanol production plant, developed by the TA’ZIZ joint venture (ADNOC and ADQ) in partnership with Proman and located in Al Ruwais Industrial City, Abu Dhabi.

LILAMA 10 personnel carrying out steel structure installation works

With a designed production capacity of 1.8 million tonnes of methanol per year, the project has an estimated EPC investment value of approximately US$1.7 billion, with Samsung E&A serving as the EPC contractor. The plant uses natural gas as its feedstock and is designed to operate using clean electricity from the power grid, thereby enhancing energy efficiency and reducing its environmental impact.

This is one of the key projects in Phase 1 of the TA’ZIZ Chemicals Industrial Complex, playing an important role in Abu Dhabi’s strategy to develop its chemicals industry and strengthen its industrial position.

LILAMA 10 personnel carrying out piping installation works

LILAMA 10 Completes More Than 6,000 Tonnes of Industrial Modules in Phase 1

At the project, LILAMA 10 is responsible for the construction and installation of structural components, electrical systems and piping on industrial modules.

The execution of these works requires close coordination among multiple disciplines, from structural works and electrical system installation to piping fabrication and assembly, ensuring overall integration, quality and compliance with the project’s technical requirements.

LILAMA 10 personnel carrying out electrical system installation works

Upon completion, the modules are assembled, inspected and trial-fitted at Hyundai Eco Vina’s port facility in Quang Ngai, Vietnam, before being dismantled, packed and shipped by sea to the project site in the UAE for installation.

LILAMA 10 personnel carrying out inspection and trial assembly of the modules

As of 3 November 2026, the sixth and final module of Phase 1 officially departed from Quang Ngai Port. LILAMA 10 has completed and handed over to its partner the entire Phase 1 scope, comprising more than 6,000 tonnes of modules, ready for installation at the project site.

Lifting and loading the modules onto the vessel for transportation to the project site

This achievement not only reflects the volume of work completed but also demonstrates LILAMA 10’s ability to execute multiple technical disciplines in an integrated manner on large-scale, complex industrial modules, while meeting the requirements of international industrial projects.

Building on Its Track Record in International Green Hydrogen Projects

LILAMA 10’s participation in the TA’ZIZ Methanol Project further builds on the Company’s track record in the fabrication, assembly and construction of industrial modules for international energy and chemical projects.

Previously, LILAMA 10 participated in the fabrication and installation of green hydrogen electrolysis modules for the West Coast project in California, USA, featuring 20 MW modules, as well as the NEOM Green Hydrogen Project in Saudi Arabia – one of the world’s largest green hydrogen projects.

The experience gained from these projects provides a solid foundation for LILAMA 10 to further leverage its capabilities in construction management, multidisciplinary coordination, quality control and compliance with international technical standards in industrial modularization.

Strengthening Construction Capabilities and International Integration

The completion of more than 6,000 tonnes of modules in Phase 1 of the TA’ZIZ Methanol Project marks a notable milestone in the development of LILAMA 10’s capabilities.

Drawing on its experience in domestic and international energy and heavy industrial projects, together with a team of experienced engineers, technical personnel and skilled workers, LILAMA 10 continues to demonstrate its capacity to undertake industrial-scale fabrication, structural steel construction, electrical system installation, piping installation and module assembly.

The sixth and final module of Phase 1 departing Hyundai Eco Vina Port on 3 November 2026, en route to the project site

From green hydrogen projects in the United States and NEOM in Saudi Arabia to the TA’ZIZ Methanol Project in the UAE, LILAMA 10 is steadily expanding its presence on the international industrial landscape, affirming the standing and capabilities of a Vietnamese mechanical engineering and installation company within the global supply chains for energy and industrial projects.

LILAMA 10 – Safety – Quality – Schedule.