This afternoon, April 27, 2021, Power Project Management Unit 2 (Electricity of Vietnam - EVN) held the signing ceremony of package 37 (XL-05) for construction and installation of the expanded Ialy Hydroelectric Project with the Union. Name of contractor: LILAMA10 Joint Stock Company - Lung Lo Construction Corporation - Truong Son Construction Corporation - Song Da Corporation - Vietnam Construction and Import-Export Joint Stock Corporation.

This afternoon, April 27, 2021, Power Project Management Unit 2 (Electricity of Vietnam - EVN) held the signing ceremony of package 37 (XL-05) for construction and installation of the expanded Ialy Hydroelectric Project with the Union. Name of contractor: LILAMA10 Joint Stock Company - Lung Lo Construction Corporation - Truong Son Construction Corporation - Song Da Corporation - Vietnam Construction and Import-Export Joint Stock Corporation.

The main construction items of the package include: Construction, equipment installation of main work items such as inlet and channel, water tunnel, pressure tower, pressure pipeline, factory. , discharge channel, TN water retaining wall, stable treatment of slopes and anti-rolling rock, T1 channel and factory flow channel.

Construction of work items in service of construction such as: dyke for water intake; underground and T2 diversion wall; auxiliary tunnels and construction niches; construction - operation roads; material storage yard.

Other preparatory and auxiliary works for construction and requirements for safety, health, environment and society.
At the ceremony, Mr. Duong Quang Thanh - Chairman of EVN's Member Council said that EVN asked the Power Project Management Board 2 to coordinate with the contractor consortium to focus on resources, human resources and equipment to soon start the construction work. The process to construct the embankment is completed before the water storage phase of the existing Ialy reservoir; Ensure the progress and quality of the work, implement the HSE (health - safety - environment) management system, comply with strictly control processes to minimize the impact on the social environment during the construction process in accordance with the provisions of the contract.

Notably, before being awarded the package 37 (XL-05) (construction and installation of the expanded Ialy Hydroelectric Project), LILAMA10 Joint Stock Company has been in charge of executing many key projects in the country and including: Hoa Binh Hydroelectricity, Son La Hydropower Plant, Lai Chau Hydropower Plant, Huoi Quang Hydropower Plant, Ban Chat Hydropower Plant, Thuong Kon Tum Hydropower Plant, Nam Ngum Hydropower Plant, Nam Theun 1 Hydropower Plant (Laos), Sendje Hydroelectricity (Equatorial Guinea), Nghi Son 2 Thermal Power Plant, Song Hau 1 Thermal Power Plant, Long Son Refinery and Petrochemicals, Lao Cai Copper Refinery, ...