LILAMA10 Joint Stock Company: Successfully burning coal for Unit 2, Nghi Son 2 Thermal Power Plant Project
Nghi Son 2 thermal power plant project in Tinh Gia district, Thanh Hoa province has successfully tested coal burning for unit 2. The plant has a total capacity of 1,200MW, including 2 units using super coal burning technology. due date.
In fact, Vietnam Machinery Erection Corporation (LILAMA), LILAMA10 Joint Stock Company and contractors have completed all construction items of unit 2 and are ready for the coal burning milestone since the end of October. 2021. However, due to some objective factors between the general contractor Doosan and the investor, the coal burning milestone of unit 2 must be postponed to the end of November 2021.
In the Nghi Son 2 thermal power plant project, LILAMA undertakes the construction and installation of 90% of the volume of mechanical and electrical equipment, of which LILAMA10 Joint Stock Company undertakes the construction:
Package BOP Turbine and some factory ancillary systems.
Neutralization pipeline system and slag discharge system.
The project is invested by Marubeni and Kepco Joint Venture, Doosan Heavy Industry Group is the EPC general contractor. The plant has a total capacity of 1,200MW, including 2 units using supercritical coal burning technology.
In order to ensure the progress of the installation of construction items to promptly hand over to the General Contractor Doosan - the Investor to operate the commercial power plant in accordance with the contract commitment, LILAMA 10 Joint Stock Company has made a progress Mobilization of human resources to meet the progress of the project completion.
Up to now, LILAMA10 has completed 100% of the work at Nghi Son 2 thermal power project and is in the process of finalizing materials and volumes.
In the context of the complicated development of the Covid-19 epidemic, LILAMA10 Joint Stock Company, performing the work at Nghi Son 2 thermal power project, always attaches great importance to the task of both construction and ensuring room safety. Anti-epidemic for employees is a top priority.